CALIBRATION DESCRIPTION
K0553 Revision D 115 [EN] English
Calibration description
The date of calibration adjustment is logged and stored during this procedure. It is important
that the ADTS Touch clock date is checked before starting a calibration adjustment or an incor-
rect date may be recorded. Instructions for checking and setting the time and date can be found
in section Settings.
“As found” data does not have to be recorded before an adjustment to the selected channel has
been carried out. Record “as found” date as required.
Preliminary operations
1) Review and become familiar with the whole procedure before beginning the calibration
process.
2) Allow at least two hours for the ADTS to thermally stabilize after switching on and before
performing any calibration routines.
3) Before starting a calibration procedure carry out a leak test, see section ADTS leak check).
4) The pressure reference level of the ADTS is the top face of the front panel when the front
panel is facing upwards, see also, section Positioning the ADTS. In calibration check mode
the ADTS sets its altitude correction to zero.
Calibration check
This procedure checks the calibration accuracy without adjusting it. It may be used either to see
if the system requires a calibration or to verify performance following a calibration adjustment.
1) Ensure the standard and the ADTS are at atmospheric pressure.
2) Connect your calibration standard to the Ps or Pt channel.
3) Open the “Tools” menu, select “Calibration (Calibrate sensors), enter your PIN, select
“Sensor”, “Calibration check” sub-menu showing the current values for Ps and Pt.
4) Apply pressure to the selected channel to Full Scale (FS) and lowest point, repeat this
process a minimum of three times.
5) Adjust the calibration standard to apply pressure to the Ps or Pt channel. To decide if the
applied pressure is stable ensure that the value of the ADTS displayed pressure equivalent
to a resolution of 0.001 mbar is stable, within ±0.001 mbar, and free from “creep”. Calculate
the actual applied pressure reading to at least 4 decimal places. No data is entered to the
ADTS when performing a calibration check. Reference pressure entries are for the sensor
adjustment operation only.
6) The leak rate must be low enough to prevent the primary standard dead weight tester
piston from moving outside the mid operating point during the calibration procedure.
7) Compare the applied pressure value on the calibration standard to the value displayed on
the ADTS and record the difference.

Table of Contents

Other manuals for GE ADTS542F

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE ADTS542F and is the answer not in the manual?

GE ADTS542F Specifications

General IconGeneral
BrandGE
ModelADTS542F
CategoryTest Equipment
LanguageEnglish

Related product manuals