Rockwell Automation Publication 750-IN118A-EN-P - May 2021 45
Chapter 3
Mechanical and Electrical Installation
Perform the steps in this chapter after the steps in Prepare for Installation on
page 33. The installation of the configured bays and other components of the
PowerFlex® 755T Drives Configured to Order Program consists of the
following principal tasks:
• Unpack the product and prepare it for installation
• Mechanically install the bays
• If your product includes multiple shipping sections, make the electrical
interconnections between the bays that are part of different shipping
sections
• Make the electrical connections to the input power supply and motor
(Chapter 4 on page 93
)
Perform the steps in this chapter in the order listed:
Remove Side and Top
Packaging
If there is any packaging on the sides and top of the shipping section, remove
it. Packaging may include plastic wrapping and a wood crate. Save any
documentation packaged in the plastic wrapping.
Topic Page
Remove Side and Top Packaging 45
Remove Detached Installation Hardware 46
Remove Shipping Skid and Cleats 47
Prepare Bay Interiors for Installation 48
Attach Floor Mounting Hardware to the Bays 50
Position the First Bay 50
Place an Additional Bay Into the Lineup 51
Remove Lifting Hardware 54
Place the IP54, UL Type 12 Roof Assemblies 54
Install Bay Joining Hardware 57
Secure Roof Assemblies 60
Secure Floor Mounting Hardware to the Floor 60
Make Bay-to-Bay Electrical Connections
For this step, use the information in the following
sections:
60
Electrical Connections Made to Each Configured
Bay During Installation
61
Component and Connection Locations 64
Bay to Bay Connection Hardware 84