Putting the machine into operation for the first time and running-in period
Before putting the machine into operation for the first time, check it
visually for exterior damage due to transport, and check whether the
equipment supplied with the machine is complete.
• Check the fluid levels according to chapter “Maintenance”.
Each machine is correctly adjusted and checked before it is delivered.
Handle the machine carefully during its first 50 operating hours.
• Do not load a cold engine.
• Warm up the machine at low engine speed and little load, do not warm
it up at a standstill.
• Do not change engine speed abruptly.
• Avoid using the machine under heavy loads and/or at high speeds.
• Avoid abrupt acceleration, braking and changing traveling direction.
• Do not run the engine at high speed for extended periods.
• Strictly observe the maintenance plans and perform (or have
performed) the specified maintenance on or with the machine –
see chapter “7.2 Maintenance overview” on page 7-2.
Traveling on public roads
The machine is not certified for travel on public roads.