Commissioning of the drive application with the »Engineer«
3.4.3 Load the Lenze setting
In order to be able to take a defined state as a basis for this commissioning, you have to
load the Lenze setting.
Start the action with C002/1
=1.
Tip!
How to load the Lenze setting using the »Engineer« is described in chapter Load
Lenze setting ( 58).
3.4.4 Make motor settings
Enter the data of your motor into the field marked with the arrow if it is not a power-
adapted standard motor:
Note!
After the Lenze setting has been loaded, the "action ready" status is reported
with C002/1
=0.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Lenze L-force 8400 BaseLine D and is the answer not in the manual?

Lenze L-force 8400 BaseLine D Specifications

General IconGeneral
BrandLenze
ModelL-force 8400 BaseLine D
CategoryInverter Drive
LanguageEnglish

Related product manuals