Start-up 115
Safe Torque Off (STO) acceptance test
Drive commissioning is not complete until the STO function has been tested.
The acceptance test of the safety function must be carried out by an authorized
person with expertise and knowledge of the safety function. The test must be
documented and signed by the authorized person.
See Appendix: Safe Torque Off (STO) on page 173.