Maintenance 2. General Maintenance
118 VT Rev.1
2.2 Overhaul (Parts Replacement)
CAUTION
Overhaul timing is based on an assumption that all joints are operated for equal
distance. If a
particular joint has a high duty or high load, it is recommended to
overhaul all joints (as many as possible) before exceeding 20,000 operation
hours with the joint as a basis.
The parts for the manipulator joints may cause accuracy decline or malfunction due to
deterioration of the manipulator resulting from long term use. In order to use the
manipulator for a long term, it is recommended to overhaul the parts (parts replacement).
The time between overhauls is 20,000 operation hours of the Manipulator as a rough
indication.
However, it may vary depending on usage condition and degree of the load (such as when
operated with the maximum motion speed and maximum acceleration / deceleration in
continuous operation) applied on the Manipulator.
For EPSON RC+ 7.0, the recommended replacement time for the parts subject to
maintenance (motors, reduction gear units, and timing belts) can be checked in the
[Maintenance] dialog box.
Refer to the Maintenance: 4. Alarm.
Note:
The recommended replacement time for the maintenance parts is when it reaches the L10
life (time until 10% failure probability). In the [Maintenance] dialog box, the L10 life is
displayed as 100%.
NOTE

Table of Contents

Other manuals for Epson VT6L

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Epson VT6L and is the answer not in the manual?

Epson VT6L Specifications

General IconGeneral
BrandEpson
ModelVT6L
CategoryRobotics
LanguageEnglish

Related product manuals