Commissioning
8.3 Checklist prior to commissioning
SIMOTICS M-1FE2 built-in motors
168 Hardware Installation Manual, 04/2020, A5E50074509B AA
8.3 Checklist prior to commissioning
The following chapter describes the checks of the completely installed machine or system
prior to commissioning.
Note
Required checks
The lists below do not purport to be complete. It may be necessary to perform additi
onal
checks and tests in accordance with the situation specific to the particular instal
lation site.
Before commissioning the system, check that it is properly installed and connected.
Commission the drive system according to the operating instructions of the converter or
inverter being used.
Precondition
The machine or system is fully installed and connected.
All safety equipment is connected and functional.
Procedure
Check the machine or system according to the following checklists and record the results.
Checklist (1) - General checks
Thoroughly familiarize yourself with the safety instructions and observe the checklists below
before starting any work.
Check
OK
Are all of the necessary components of the configured drive line-up available, correctly
dimensioned, installed and connected?
Is the manufacturer documentation for the system components (e.g. drive system,
encoder, cooling system, brake) and the "SIMOTICS M-1FE2 built-in motors" Configu-
ration Manual available?
If you want to operate the 1FE2 motor on the SINAMICS S120 drive system, is the
following, up-to-date SINAMICS documentation available?
SINAMICS S120 Commissioning Manual
Getting Started S120
S120 Function Manual
S120/150 List Manual
SINAMICS S120 Equipment Manual
If you want to operate the 1FE2 motor on the SINAMICS S120 drive system, make
sure that the "Checklists for commissioning SINAMICS S" in the SINAMICS S120
Commissioning Manual have been observed.
Is the motor type to be commissioned known?
(e.g. 1FE2 _ _ __ _ _ _ __ _ _ _)
Are the environmental conditions in the permissible range?
The documentation on SINAMICS S120 can be found under the following link
(
https://support.industry.siemens.com/cs/products?dtp=Manual&mfn=ps&pnid=13231&lc=de
-DE)

Table of Contents

Other manuals for Siemens SIMOTICS Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens SIMOTICS Series and is the answer not in the manual?

Siemens SIMOTICS Series Specifications

General IconGeneral
BrandSiemens
ModelSIMOTICS Series
CategoryEngine
LanguageEnglish

Related product manuals