ABB Network Partner AB
- 1Page
Function:
1 Receiving and storage
Remove the terminal from its transport case and perform a visual inspec-
tion of any possible transport damages. Check that the delivered terminal
has the correct data on the rating plate at the front of the terminal, that is,
rated current, rated voltage, and rated dc voltage.
If the terminal is to be stored before installation, this must be done in a
dry, dust-free place, preferably in its original transport case.
2Installation
2.1 Mechanical installation This terminal is built in the mechanical packaging system described in
the Buyer’s Guide Series REx 500 Mechanical design and mounting
accessories (1MRK 514 003-BEN).
Depending on how the terminal is to be mounted, a suitable mounting kit
is used. For 19-inch rack mounting, flush mounting, and wall mounting,
you can order mounting kits that contain all parts needed for the mount-
ing, including screws and an assembly instruction.
Avoid dusty, damp places or conditions that cause rapid temperature vari-
ations, powerful vibrations, or shocks.
2.1.1 19” rack installation For mounting the terminal in a 19-inch rack, you need mounting angles.
The type of mounting angles depends on the size of the terminal.
You can mount each mounting angle on either side of the terminal. Mount
the angles on the terminal with the included screws according to Fig. 1.
All included screws have TORX T20 type grips.
3
Installation and commissioning
1MRK 580 166-XEN
Version 1.0-00
October 1996
Basic