2 GENERAL GUIDELINES
General Electric IEDs are self-checking devices and will raise an alarm in the unlikely event of a failure. This is why
the commissioning tests are less extensiv
e than those for non-numeric electronic devices or electro-mechanical
relays.
To commission the devices, you (the commissioning engineer) do not need to test every function. You need only
verify that the hardware is functioning correctly and that the application-specific software settings have been
applied. You can check the settings by extracting them using the settings application software, or by means of the
front panel interface (HMI panel).
The menu language is user-selectable, so you can change it for commissioning purposes if required.
Note:
Remember to restore the language setting to the customer’s preferred language on completion.
Caution:
Before carr
ying out any work on the equipment you should be familiar with the
contents of the Safety Section or Safety Guide SFTY/4LM as well as the ratings on the
equipment’s rating label.
Warning:
With the exception of the CT shorting contacts check, do not disassemble the device
during commissioning.
Chapter 21 - Commissioning Instructions P14x
490 P14xEd1-TM-EN-1

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE MiCOM P145 Agile and is the answer not in the manual?

GE MiCOM P145 Agile Specifications

General IconGeneral
BrandGE
ModelMiCOM P145 Agile
CategoryControl Unit
LanguageEnglish

Related product manuals