GE HEALTHCARE
D
IRECTION 5305880-100, REVISION 3 LOGIQ™ 100 PRO SERVICE MANUAL
Chapter 2 - Pre Installation Page 2-5
2-2-5 Time and Manpower Requirements
Site preparation takes time. Begin Pre installation checks as soon as possible, if possible, six weeks
before delivery, to allow enough time to make any changes.
2-2-6 Checklist for Installation
2-2-6-1 Checklist for Installation
Procedures Paragraph Initials
Observe Warnings Section 3-1-3
Unpack LOGIQ™ 100 PRO Section 3-2
Assemble LOGIQ™ 100 PRO Section 3-4
Perform Functional Checks Chapter 4-3
Perform Electrical Safety Tests Chapter 10-6
Table 2-6 Checklist for Installation
State: RELEASE - Document is released and under formal Change Control. Changes are subject to the ECR/ECO Process.
See the GEHC Myworkshop System to determine the status of this document.
Approved Document - 5305880-100TPH_r3.pdf Page 44 of 197