Completing the Installation
3-5-1 Power On/Boot Up
NOTE: After turning off the system, wait at least ten seconds before turning it on again. The system
may not be able to boot if power is recycled too quickly.
3-5-1-1 Scanner Power On
1.) Connect the Main Power Cable at the rear of the System.
2.) Connect the Main Power cable to an appropriate mains power outlet.
3.) Switch ON the Main Circuit Breaker at the rear of the System.
When power is applied to the Scanner, and the Rear Circuit breaker is turned ON, Power is distributed
to the Fans, Control panel, Monitor, Internal and External I/O’s, Cage Boards, Peripherals and the
Backend Processor. When the Power ON/OFF key is pressed once, the Backend Processor starts and
its software code is distributed to initiate the scanner.
WARNINGWARNING
Protective earth must be taken when connecting AC power cable (200V) without its plug
to wall outlet.
Figure 3-13 Circuit Breaker
Main Power Cable
Main Circuit Breaker