GENERAL
This section provides procedures for installing the hoist
cable on the hoist drum, cable reeving, and erecting and
stowing the boom extension.
NOTE: For information on synthetic rope refer to the
separate manual.
INSTALLING CABLE ON THE HOIST
Refer to Figure 6-1.
NOTE: Straighten cable before installing on hoist drum.
1. Place cable (1) over boom nose sheave and route to
hoist drum (2).
2. Rotate hoist drum so cable slot located on left side of
drum is easily accessible.
3. Insert cable through slot (3) and wedge block (4). Loop
around anchor wedge (6) and route back through wedge
block to clamp (5). Ensure cable is routed over guide in
side of drum. End of cable should extend approximately
50 mm (2 in) beyond clamp. Tighten clamp.
4. Adjust cable so clamp side is snug against guide.
Position anchor wedge in wedge block. Pull firmly on
inside hoist side of cable to secure the wedge.
5. If wedge does not seat securely in slot, carefully tap
cable and top of wedge (7) with a mallet.
6. Slowly rotate drum and evenly wind first layer of cable.
7. Install remainder of cable as required.
CABLE REEVING
NOTE: There are two types of cable (rope) available on
this crane; 35 x 7 (non-rotating) and 22 mm
synthetic.
Within the limits of the load and range charts and permissible
line pull, multi-part lines allow the operator to raise a greater
load than can be raised with a single part line. Various cable
reeving (part line) is possible with the boom nose and hook
block (Figure 6-8 through Figure 6-14). This reeving should
be accomplished by a qualified rigger using standard rigging
CAUTION
If cable is wound from storage drum, rotate reel in same
direction as hoist.