Global Telecom Solutions Sector
68P80801E30-A 5/1/2002 1301 E. Algonquin Road, Schaumburg, IL 60196 5-1
Chapter 5
Final
Checkout
Chapter Overview
This chapter describes the final checkout procedures to be performed after
installation of the EBTS equipment is complete. Refer to the EBTS System
Manual (on CD: 98P80800A17) for the final checkout of non-site control
equipment. The following table lists this chapter’s topics.
Section Page This section . . .
Final Checkout Setup 5-2 describes the procedures for proper
setup of the site control equipment
Powering the Site Controller
Rack
5-3 describes the procedures for
powering up the site control
equipment
Circuit Breakers 5-4 describes the procedures for setting
the circuit breakers