Table 21: Clearance Requirements for the Services Gateway
Requirement for Clearance
Recommended
ClearanceLocation
Space for service personnel to
remove and install hardware
components
2.5 in. (6.35 cm)Front of the chassis
Space for service personnel to
remove and install hardware
components
2.5 in. (6.35 cm)Rear of the chassis
Space for cable management and
organization
2.5 in. (6.35 cm)Between the front-mounting
flange and rack or cabinet edge
Space for the cooling system to
function properly and to maintain
unrestricted airflow around the
chassis
2.5 in. (6.35 cm)Between the side of the chassis
and any non-heat-producing
surface such as a wall or
cabinet side
Space for the cooling system to
function properly and to maintain
unrestricted airflow around the
chassis
2.5 in. (6.35 cm)Between the side of the chassis
and devices that have fans or
blowers
Related
Documentation
General Site Guidelines for Installing the SRX110 Services Gateway on page 40•
• SRX110 Services Gateway Cabinet Requirements on page 40
• SRX110 Services Gateway Rack Requirements on page 41
SRX110 Services Gateway Electrical and Power Requirements
You must consider the following factors while planning the electrical wiring and power
availability at your site:
•
Power specifications and requirements for the device
•
Electrical wiring guidelines for the device installation site
•
Power, connection, and power cord specifications for the device
•
Grounding guidelines and specifications for the device
Related
Documentation
• SRX110 Services Gateway Site Electrical Wiring Guidelines on page 131
• Clearance Requirements for Airflow and Hardware Maintenance of the SRX110 Services
Gateway on page 42