3. Click the Execute Button to display the Confirmation Dialog Box. Click the Yes Button to back up
the project.
4. When the backup destination is the floppy disk, the number of floppy disks required will be dis-
played. When more than one floppy disk is required, switch the floppy disks according to the
messages displayed.
Reference
♦ If the same backup file of the project already exists in the backup destination, the previously existing
backup file will be deleted and a new backup file will be created.
R
R
e
e
f
f
e
e
r
r
e
e
n
n
c
c
e
e
Restore
1. Select the Restore Tab.
2. Set the project to be restored.
1
2
No. Item Details
1 Restore
Source
When floppy disk is selected, the backup file stored in the floppy disk will be restored.
When folder is selected, the backup file stored on the hard disk will be restored.
2 Restore
Destination
Sets the name of the project file to be restored as a full path name.
Specify the name of the project file with the same name as that of the backup file. Exam-
ple: If the backup file is TEST.000, then specify the project name as TEST.IPP (any path
can be specified).
3. Click the Execute Button to display the confirmation dialog box. Click the Yes Button to restore the
project.
4. When floppy disk is set as the restore source, switch the floppy disks according to the messages