6. Tighten fixing screws (3x M12) using a tightening torque of 62 ± 6 Nm.
7. Connect gear motor [►Section 6.8, Page 66].
7.3 Commissioning the transformer at the operating site
Before commissioning the transformer, repeat the function tests.
WARNING
Danger of death or severe injury!
Danger of death or severe injury due to incorrect operation.
► Only commission the transformer once the functions have been checked
in accordance with section "Tests on the motor-drive unit".
NOTICE
Damage to motor-drive unit!
Damage to the motor-drive unit due to condensate in the control cabinet.
► Always keep the control cabinet of the motor-drive unit tightly closed.
► In the event of operation interruptions of more than 8weeks prior to initial
use, connect and operate the anti-condensation heater in the control cab-
inet. If this is not possible, place a sufficient amount of desiccant in the
control cabinet.