9.6 Do a test of the exhaust waste valve
Periodicity
Description
Weeks 1
Duration for performing preliminary requirements 0.0 man-hours
Duration for performing the procedure 0.2 man-hours
Duration for performing the requirements after job completion 0.0 man-hours
Personnel
Description Specialization QTY
Engine crew Basic 1
Support equipment
Description Part No. CSN QTY
None
Supplies
Description QTY
None
Spare Parts
Description Part No. CSN QTY
None
SAFETY PRECAUTIONS
• None
PRELIMINARY OPERATIONS
• This procedure is only applicable, if the engine has operated for a long period at low load
with the exhaust waste valve closed.
• The engine load must be less than 70%, or the engine can be stopped.
X92DF
AA00-8135-00AAA-320A-A
Operation Manual Do a test of the exhaust waste valve
Winterthur Gas & Diesel Ltd.
- 502 - Issue 002 2020-08