10.4 Examine the supply unit for fuel leakage
Periodicity
Description
Unscheduled
Duration for performing preliminary requirements 0.0 man-hours
Duration for performing the procedure 1.0 man-hours
Duration for performing the requirements after job completion 0.0 man-hours
Personnel
Description Specialization QTY
Engine crew Basic 1
Support equipment
Description Part No. CSN QTY
None
Supplies
Description QTY
None
Spare Parts
Description Part No. CSN QTY
None
SAFETY PRECAUTIONS
CAUTION
Injury Hazard: Always put on gloves and safety goggles when you do work on hot or
pressurized components. When you open the screw plugs, fuel can come out as a spray
and cause injury.
PRELIMINARY OPERATIONS
• None
X92DF
AA00-0000-00AAA-311B-A
Operation Manual Examine the supply unit for fuel leakage
Winterthur Gas & Diesel Ltd.
- 536 - Issue 002 2020-08

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the WinGD X92DF and is the answer not in the manual?

WinGD X92DF Specifications

General IconGeneral
BrandWinGD
ModelX92DF
CategoryEngine
LanguageEnglish

Related product manuals