9.8 Running-in of new components
Periodicity
Description
Unscheduled
Duration for performing preliminary requirements 0.0 man-hours
Duration for performing the procedure 72.0 man-hours
Duration for performing the requirements after job completion 0.0 man-hours
Personnel
Description Specialization QTY
Engine crew Intermediate 1
Support equipment
Description Part No. CSN QTY
None
Supplies
Description QTY
None
Spare Parts
Description Part No. CSN QTY
None
SAFETY PRECAUTIONS
• None
PRELIMINARY OPERATIONS
• This procedure is only applicable after an overhaul or an installation of new components
of the piston running system.