10.5 Examine the rail unit for leakage
Periodicity
Description
Unscheduled
Duration for performing preliminary requirements 0.0 man-hours
Duration for performing the procedure 1.0 man-hours
Duration for performing the requirements after job completion 0.0 man-hours
Personnel
Description Specialization QTY
Engine crew Basic 1
Support equipment
Description Part No. CSN QTY
None
Supplies
Description QTY
None
Spare Parts
Description Part No. CSN QTY
None
SAFETY PRECAUTIONS
CAUTION
Injury Hazard: Always put on gloves and safety goggles when you do work on hot or
pressurized components. Fuel can come out as a spray and cause injury.
PRELIMINARY OPERATIONS
• None
X92DF
AA00-0000-00AAA-311E-A
Operation Manual Examine the rail unit for leakage
Winterthur Gas & Diesel Ltd.
- 540 - Issue 002 2020-08