Procedure
1. Open the front door. Refer to section 8.1.
2. Set the manual switch to the
1
position (vertical).
Warning:
General hazard
Be careful and use both your hands to turn the manual switch. You
need some force to turn the switch.
3. Close the front door. Refer to section 8.2.
The EVSE starts. The display shows a message when the EVSE is ready for
operation.
6.4 Remove condensation from the cabinet
Preliminary requirements
Installation engineer
Owner
Note: If the EVSE is off for more than two hours, condensation can occur.
Procedure
1. Open the front and right doors. Refer to section 8.1.
2. Set the main breaker to the off position.
3. Energize the EVSE. Refer to section 6.3.
4. Close the doors. Refer to section 8.2.
5. Wait four hours.
The internal heater of the cabinet heats the inside of the cabinet and lets the
condensation evaporate.
6. Open the front and right doors. Refer to section 8.1.
7. Set the main breakers 1 and 2 to the on position.
a. Set the main breakers from the
Off
to the
Manual
position.
b. Set the main breakers from the
Manual
to the
Auto
position.
8. Close the doors. Refer to section 8.2.
6.5 Local service portal operations
6.5.1 Start the local service portal
Preliminary requirements
The EVSE is ready for
operation. No charge
session is in progress.
Installation engineer
Operation
9AKK108467A6398-EN | 002 81

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB Terra 360 CE and is the answer not in the manual?

ABB Terra 360 CE Specifications

General IconGeneral
BrandABB
ModelTerra 360 CE
CategoryBattery Charger
LanguageEnglish

Related product manuals