6.3.6.2 Creating a Power Module on the NetEco
Prerequisites
You have logged in to the NetEco client.
You have the operation rights for Data Center Planning.
You have created a management domain for the device to be added on the Data Center
Planning page.
Procedure
Step 1 Choose Configuration > Configuration Management > Data Center Planning from the
main menu. The Data Center Planning window is displayed.
Step 2 Select the management domain to add a device.
Step 3 If the management domain is a rack, DDF, or power cabinet, click the management domain
and choose Design under . The page for adding a device is displayed. Otherwise, skip this
step.
Step 4 In the lower-left corner of the page, click the Device tab.
Step 5 Click the drop-down list box in Type and select RPDU.
Step 6 Select the device to be added and drag its icon to the management domain.
To delete a device, click the device and choose Delete under .
Step 7 Specify parameters shown in Figure 6-40 in the right pane based on the following table. The
power module complying with the SNMP v3 protocol is used as an example.