iManager NetEco 6000
Device Installation and Commissioning Guide
3 Installing Devices
Copyright © Huawei Technologies Co., Ltd.
20
----End
3.5 Installing an independent deployment AI/DI unit
Procedure
Step 1 It is recommended that the independent deployment AI/DI unit be installed on the top rack
rail in the rear of the network cabinet.
Plan the installation position for the independent deployment AI/DI unit based on the cable routes in the
network cabinet, and install the independent deployment AI/DI unit at the planned position in the
network cabinet.
Figure 3-9 Installing an independent deployment AI/DI unit
----End
3.6 Installing Sensors
3.6.1 Installing a NTC Temperature Sensor
Context
Temperature sensors should be installed inside cabinets. The number of temperature
sensors to be installed inside each cabinet depends on the customer requirement. This
section describes how to install six temperature sensors inside each cabinet.
Six temperature sensors should be installed in each cabinet, one each at the 11 U, 22 U,
and 33 U positions in the front and rear door frames.
Table 3-1 Mapping between the number of temperature sensors and the installation positions
Number of temperature sensors
Installation positions
2
22U
4
22U, 33U
6
11U, 22U and 33U

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei iManager NetEco 6000 and is the answer not in the manual?

Huawei iManager NetEco 6000 Specifications

General IconGeneral
BrandHuawei
ModeliManager NetEco 6000
CategoryServer
LanguageEnglish

Related product manuals