Step 5 Place the water detection cable onto the fastener, secure the fastener, and keep the water
detection cable in close contact with the floor.
Figure 3-29 Securing a water detection cable
----End
3.7 Installing the Video Management System
3.7.1 Installing the VCN500
Procedure
Step 1 Determine the mounting holes for the VCN500 in the network cabinet based on the
engineering layout diagram, adjust the guide rails or trays, and install floating nuts.
Step 2 Place the VCN500 into the network cabinet with caution, and gently press buttons on the
upper and lower mounting ears.
Figure 3-30 Placing the VCN500
Step 3 Tighten the captive screws on the mounting ears using a Phillips screwdriver, and then close
the mounting ear buttons.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei iManager NetEco 6000 and is the answer not in the manual?

Huawei iManager NetEco 6000 Specifications

General IconGeneral
BrandHuawei
ModeliManager NetEco 6000
CategoryServer
LanguageEnglish

Related product manuals