Appendix C _____________________________________________ Installation and Test Procedures
VAISALA______________________________________________________________________ 361
APPENDIX C
INSTALLATION AND TEST
PROCEDURES
C.1 Overview
These installation and test procedures are designed to assist Vaisala field
engineers and customers with the installation and testing of the RVP900 on
a radar system. Because these test procedures also function as an
installation procedure, they must be completed in order. Failure to perform
one step may effect later tests.
A copy of the test results should be kept either on file or with the RVP900
Digital IF Receiver and Signal Processor User’s Manual. Do not write in
the manual since it will be replaced with an upgrade; make a copy and
mark that.
Each test should be performed and signed off when it is completed. If a test
does not pass, then the problem should be remedied and the test repeated.
If the test still does not pass, then an additional sheet should be added to
the test explaining the variance. A supplementary test sheet is at the end of
the test procedure.
Customer: _____________________________________
Serial No. Main: _____________________________________
IFDR: _____________________________________
Delivery Date: _____________________________________
Radar Mfg./Type: _____________________________________
_____________________________________
Customer Engineer: _____________________________________
Vaisala Engineer: _____________________________________