Advant
®
Controller 450 User’s Guide
Section 2.5.1 Safety Regulations
3BSE 002 415R701 Rev A 2-69
2.5.1 Safety Regulations
The instructions given in Section 2.2.1, Safety Regulations are applicable in all situations when
you work with an Advant Controller and associated equipment. Please read the instructions
carefully. One instruction is highlighted:
DANGER
Work with care when supply voltage is applied in the system. The voltage in
the cabinet can cause injury and can even kill a human being.
2.5.2 Servicing Tool
Installation of an engineering station, the main servicing tool, is described in Section 2.4.2.3,
Connection of Engineering Station. Detailed information for its use is given in separate
documentation.
2.5.3 Commissioning
2.5.3.1 General
For a general description of how to set the controller in operation and start the execution of an
application program, see
Section 2.4.2.7, Summary of the Controller Start-up and Verification
of the Start.
Below, you can find general information on some function tests which you can perform to verify
the product. Short notes on adequate facilities provided by the engineering station are also
listed.
For a more detailed description, see the AMPL Configuration Advant Controller 400 Series,
Reference Manual.
2.5.3.2 Procedure
The application program is normally checked, one executing unit at a time. This is done by
deblocking the complete PC program (DIBM command) and successively deblocking the
execution units, one after the other. You can, for example, check that a flow valve functions and
then verify the start sequence for a pump motor, and so on.
After each sub-function is tested, a comprehensive function control is performed to verify that
all execution units function together.
Finally, a full scale check of the complete installation is performed to verify that the program is
in accordance with the plant specification.