CHAPTER 7
Planning and Preparing the Site
IN THIS CHAPTER
General Site Guidelines | 61
Site Electrical Wiring Guidelines | 61
SRX3600 Services Gateway Physical Specifications | 62
SRX3600 Services Gateway Environmental Specifications | 64
Site Preparation Checklist for the SRX3600 Services Gateway | 65
General Site Guidelines
Efficient device operation requires proper site planning and maintenance and proper layout of the equipment,
rack or cabinet (if used), and wiring closet.
To plan and create an acceptable operating environment for your device and prevent environmentally
caused equipment failures:
•
Keep the area around the chassis free from dust and conductive material, such as metal flakes.
•
Follow prescribed airflow guidelines to ensure that the cooling system functions properly and that
exhaust from other equipment does not blow into the intake vents of the device.
•
Follow the prescribed electrostatic discharge (ESD) prevention procedures to prevent damaging the
equipment. Static discharge can cause components to fail completely or intermittently over time.
•
Install the device in a secure area, so that only authorized personnel can access the device.
Site Electrical Wiring Guidelines
Table 12 on page 62 describes the factors you must consider while planning the electrical wiring at your
site.