5.3.4.5 Initialization of central station
The procedure for initialization of the group setting and the optional setting is as follows.
Changing to self check mode
Depress the “GROUP (
)” and ”MODE” switches simultaneously, the central station is changed to the self check
mode. In case that there is a group in operation, the “NO FUNCTION” is indicated and the central station can not be
changed to the self check mode.
After changing to the self check mode, the LCD indication is changed as shown below. Then, depress the
“GROUP(
)” and “MODE” switches simultaneously again, and the central station is changed to the initializing mode.
NOTE
In case that the “GROUP ()” and ”MODE” switches are not depressed again, the self check operation continues.
Initialization of EEPROM
When the central station is changed to the initializing mode, the LCD indication on the central station is as shown below.
In this condition, depress the “RESET” switch, and the ickering “06” indication is changed to ON and the initialization is
performed.
(In case that initialization is not required, depress the “CHECK” switch, the LCD indication is automatically changed as
shown below.)
“06” ickers. Depress “RESET” switch
and “06” is changed to ON.
In case of EEPROM initialization, it
takes approximately 60–90 seconds.
To connection check
5 Centralised remote controls
PSC-A64S
TCGB0106 rev.0 - 12/2014
393