1) Use a leak tester to check hoses and pipes for any gas leakage.
2) Check each hose or pipe clamp for tightness.
Retighten or replace loose clamp as required, if any.
REMOVAL
1) Recover refrigerant by using recovery and recycling equipment.
Be sure to follow the instruction manual for the equipment.
The amount of compressor oil removed must be measured and
the same amount must be added to the system when reinstal-
ling.
2) Replace defective hose or pipe.
CAUTION:
As soon as the above hose or pipe is disconnected, cap
its opened fitting to prevent moisture and dust from en-
tering.
INSTALLATION
1) Reverse removal procedure to install refrigerant line.
2) Evacuate and charge system. Refer to “EVACUATING” and
“CHARGING” in this section.
INSPECTION OF IDLE SPEED WITH A/C ON
For G16 and J20 engines model, refer to Section 6E1.
For H25 engine model, refer to Section 6E2.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Suzuki sq-416-420-625 and is the answer not in the manual?

Suzuki sq-416-420-625 Specifications

General IconGeneral
BrandSuzuki
Modelsq-416-420-625
CategoryAutomobile
LanguageEnglish

Related product manuals