YH4
GRAND
VITARA
HEATER AND VENTILATION 1A-7
1. Fastening nuts
1. Air flow
BLOWER MOTOR
REMOVAL
1) Disconnect negative (–) cable at battery.
2) Disable air bag system, if equipped. Refer to DISABLING AIR
BAG SYSTEM in Section 10B.
3) Remove ECM with bracket from blower motor unit.
4) Disconnect harness clamps from dash panel.
5) Loosen three nuts fastening blower unit.
6) Disconnect blower motor lead wire at coupler (2).
7) Remove blower motor (3) from blower unit (1).
INSPECTION
Check continuity between terminal to terminal as shown in left fig-
ure.
If check results are continuity, proceed to next operation check.
If not, replace.
Connect battery to blower motor as shown, then check that the
blower motor operates smoothly and specified current.
Specified current: Max. 25 A at 12 V
INSTALLATION
1) Reverse removal procedure for installation.
2) Enable air bag system, if equipped. Refer to ENABLING AIR
BAG SYSTEM in Section 10B.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Suzuki sq-416-420-625 and is the answer not in the manual?

Suzuki sq-416-420-625 Specifications

General IconGeneral
BrandSuzuki
Modelsq-416-420-625
CategoryAutomobile
LanguageEnglish

Related product manuals