The network test and line test of the installed CC-Link module can be conducted.
POINT
1. Execute the network test and line test when the installed CC-Link module is
online.
When it is offline, the network test and line test are not executable.
2. Perform the line test (Selected station) when an error is detected in the line
test (All stations).
When the line test (All stations) result is normal, the line test (Selected
station) need not be performed.
3. When a communication error has occurred during connection, make the
connection target setting again.
(1) Test screen
Figure 9.66 Test screen