Perform tests
Note
You must ensure the safety of your installation. Before the nal commissioning of a system, you
should perform a complete function test and the necessary safety tests.
In the tests, also plan for foreseeable possible errors. In this way, you avoid putting persons or
plant at risk during operation.
7.11.2 Requirements for commissioning
Requirements
Table 7-8 Requirement for commissioning
Step Prior Activity See...
1 ET 200iSP is installed. Section "Installing (Page 101)"
2 The network parameters of the ET 200iSP are
set:
Section "Wiring (Page 119)"
• Network parameters
(Ethernet address; subnet mask)
Section "Conguring the PROFINET connec‐
tion (Page 179)"
• Setting the PROFIBUS address,
Section "Conguring PROFIBUS DP address
(Page 179)"
3 ET 200iSP is wired. Section "Wiring (Page 119)"
4 Zone 1, zone 21, zone 2 and zone 22: Addi‐
tional check (inspection) of the installation
and wiring of ET 200iSP, connections, enclo‐
sure and supply line.
5 ET 200iSP is congured (and parameters as‐
signed)
Section "Basics of commissioning and diag‐
nostics (Page 155)"
6 Supply voltage for the higher-level bus com‐
ponents is switched on.
Documentation of the higher-level bus com‐
ponents
• IO controller and media converter
• DP master and PROFIBUS coupler
7 Higher-level bus components are in RUN
mode
Documentation of the higher-level bus com‐
ponents
• IO controller and media converter
• DP master and PROFIBUS coupler
Commissioning and Diagnostics
7.11 Commissioning and starting up the ET 200iSP
ET 200iSP
178 Operating Instructions, 11/2022, A5E00247483-AK