User manual of EC160 elevator intelligent integrated machine Debugging at fast speed
153
Chapter 8 Debugging at fast speed
8.1 Inspection and confirmation of the electrical assembly
1. The connections of the engine room and beam are correct.
2. The connection and installation size of the leveling switch on the car top are correct.
3. All safety switches in the hoistway can act validly.
4. The installation position of the up/down limit switches in the hoistway is correct and the
switches can act validly.
5. The installation position of the up/down limit switches is correct and the switches can act
validly.
6. The installation position of the up/down forced deceleration switches are correct and the
switches can act validly.
Terminal deceleration switch: if the speed of the elevator is less than 1.75m/s, install SDS1 and
SUS1; if the speed of the elevator is between 2.0~3.0m/s, install SDS2 and SUS2. For details,
refer to 4.5.1 Electrical installation of hoistway.
7. The connection of the interphone is correct and can work normally.
8. The connection of the arrival gong is correct.
9. The connection of the calling communication board is reliable and correct.
10. Switch off the main power supply and check the communication wires.
(1) check whether the terminal resistor on DC-03F board in the car is short circuited.
(2) measure the module cable of the hoistway communication to keep about 60.
(3) measure the module cable of the car communication to keep about 60.
11. The connections of the car light and fan are correct.
8.2 Power on and check
1. Following steps need to be confirm and check after the action in section 1:
(1) Switch off the power supply.
(2) Ensure all switches are off.
(3) Ensure all inspection/automatic switches are in the inspection position and the emergency-stop
switch is pressed.
(4) Ensure there is nobody in the hoistway and car and the elevator is in the safe condition.
(5) Ensure the running of the elevator is not affected by the outside.
2. Inspection and debugging of the door operator
(1) Switch on the power supply.
(2) Restore the emergency-stop switch of the control cabinet.
(3) Switch on the power supply of the door operator of the control cabinet and the

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the INVT EC160 and is the answer not in the manual?

INVT EC160 Specifications

General IconGeneral
BrandINVT
ModelEC160
CategoryControl Systems
LanguageEnglish

Related product manuals