EasyManuals Logo
Home>Huawei>Storage>FusionModule2000-S

Huawei FusionModule2000-S User Manual

Huawei FusionModule2000-S
346 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #344 background imageLoading...
Page #344 background image
Electric Installation Checklist
No. Check Item Check Result
1 All ground cables are copper cables with
diameters meeting the requirements. No switch or
fuse is installed on a ground cable, and no open
circuit occurs.
□ Passed □ Failed
2 All PE cables, AC input cables, and intra-cabinet
cables are connected correctly according to the
power system circuit diagram, and all screws are
fastened. The input and output cables are not
short-circuited.
□ Passed □ Failed
3 Power cables and ground cables are not coiled
and excess parts are cut o.
□ Passed □ Failed
4 Lugs for power cables and ground cables are
welded or crimped securely.
□ Passed □ Failed
5 Power cables and ground cables are routed and
bound separately from other cables.
□ Passed □ Failed
11 DIP switches on devices are correctly set. □ Passed □ Failed
7.6 Acronyms and Abbreviations
A
AC alternating current
ATS automatic transfer switch
B
BCB battery circuit breaker
BIB battery control I/O board
BIM battery interface module
BSPP British Standard Pipe
Parallel Thread
BSPT British Standard Taper
Pipe Thread
FusionModule2000-S Smart Modular Data Center
User Manual 7 Appendix
Issue 07 (2022-09-30) Copyright © Huawei Technologies Co., Ltd. 333

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei FusionModule2000-S and is the answer not in the manual?

Huawei FusionModule2000-S Specifications

General IconGeneral
BrandHuawei
ModelFusionModule2000-S
CategoryStorage
LanguageEnglish

Related product manuals