EasyManuals Logo
Home>GE>Relays>750

GE 750 User Manual

GE 750
504 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #425 background imageLoading...
Page #425 background image
GE Power Management 750/760 Feeder Management Relay 17-
19
17 COMMISSIONING 17.6 METERING
17
17.6.10 MEASUREMENT OF APPARENT POWER DEMAND
Test Connections per Figure 17–1: RELAY TEST WIRING – WYE CONNECTION or Figure 17–2: RELAY
TEST WIRING – DELTA CONNECTION on page 17–4.
Expected Accuracy:
± 2.0% of full scale
Actual Values Displays:
Under subheading
A2 METERING \ DEMAND \ APPARENT POWER \
LAST APPARENT POWER DEMAND
MAX APPARENT POWER DEMAND (DATE, TIME)
Procedure:
Follow the procedure in Section 17.6.7: MEASUREMENT OF CURRENT DEMAND on page 17–17, except
that the injected and monitored parameter is VA.
17.6.11 CALCULATION OF PERCENT OF LOAD-TO-TRIP
Test Connections per Figure 17–1: RELAY TEST WIRING – WYE CONNECTION or Figure 17–2: RELAY
TEST WIRING – DELTA CONNECTION on page 17–4.
Expected Accuracy:
equivalent to that of phase current inputs
Actual Values Displays:
Under subheading
A2 METERING \ CURRENT \
% OF LOAD-TO-TRIP
Note:
Percent of load-to-trip is calculated from the phase with the highest current reading. It is the ratio of this current
to the lowest pickup setting among the phase time and instantaneous overcurrent protection features. If all of
these features are disabled, the value displayed will be 0.
Procedure:
Inject current of various values into phase A. Check that percent load-to-trip is calculated as the correct per-
centage of the most sensitive operational phase O/C element and displayed. Repeat for phases B and C.

Table of Contents

Other manuals for GE 750

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE 750 and is the answer not in the manual?

GE 750 Specifications

General IconGeneral
BrandGE
Model750
CategoryRelays
LanguageEnglish

Related product manuals