EasyManuals Logo
Home>GE>Relays>750

GE 750 User Manual

GE 750
504 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #454 background imageLoading...
Page #454 background image
17-
48
750/760 Feeder Management Relay GE Power Management
17.8 MONITORING 17 COMMISSIONING
17
3. Inject the preset voltage and current and note the measured delay time. Reset the timer.
4. Repeat step 3 four more times and obtain an average of the time intervals.
5. Disconnect theStop Trigger.
17.8.12 VT FAILURE
Test Connections per Figure 17–1: RELAY TEST WIRING – WYE CONNECTION or Figure 17–2: RELAY
TEST WIRING – DELTA CONNECTION on page 17–4.
1. Set
V
an
=
V
bn
=
V
cn
= nominal voltage at 0
°
, 120
°
, and 240
°
respectively, and inject into the relay. With
these balanced voltages 120
°
apart, the positive sequence voltage (
V
1
) is greater than 0.05 x VT.
2. Set I
a
= I
b
= I
c
= 1 x CT at 0
°
, 120
°
, and 240
°
respectively, and inject into the relay. With these balanced
currents 120
°
apart, the positive sequence current (
I
1
) is greater than 0.05 x CT.
3. Remove the balanced voltages so the positive sequence voltage (
V
1
) is less than 0.05 x VT. If this function
is set to “Control”, any output relays programmed for this condition should operate. If the function is set to
Alarm, check that the ALARM and MESSAGE indicators are flashing, the VT Failure alarm message is
displayed, and any output relays programmed for this condition are operated.
4. Apply the balanced voltages and the VT Failure condition should reset.
5. Now reduce
V
an
until the VT Failure condition returns. Verify the ratio of the negative sequence voltage
(
V
2
) to the positive sequence voltage (
V
1
) is 0.25 at this point. Return
V
an
to nominal and the VT Failure
condition should reset. Repeat this step for
V
bn
and
V
cn
.
6. With
V
an
=
V
bn
=
V
cn
returned to nominal voltage at 0
°
, 120
°
, and 240
°
respectively, reduce
V
an
until the VT
Failure condition returns. Now reduce
I
a
until the VT Failure condition resets. Verify the ratio of the nega-
tive sequence current (
I
2
) to the positive sequence current (
I
1
) > 0.20 at this point. Return
I
a
to nominal and
the VT Failure condition should reset. Repeat this step for
I
b
and
I
c
.
17.8.13 TRIP COIL MONITOR
1. Ensure the wiring to the circuit breaker trip and close circuits is complete.
2. Energize the breaker trip and close circuits and close the breaker.
3. Carefully disconnect a wire to open the trip circuit. After 5 seconds the element should generate an output.
4. Restore the open circuit and the element should reset.
5. If the Open Breaker permissive is Enabled, and the trip circuit wiring has been arranged to permit this
operation, open the breaker.
6. Repeat steps 3 and 4.
Indications and Operations caused by the various Functions are as outlined under Section 17.7.3:
PHASE TIME OVERCURRENT 1 on page 17–21, with the following exceptions.
There is no Trip function for this element.
17.8.14 CLOSE COIL MONITOR
1. Ensure the wiring to the circuit breaker trip and close circuits is complete.
2. Energize the breaker trip and close circuits and open the breaker.
3. Carefully disconnect a wire to open the close circuit. After 5 seconds the element should generate an output.
4. Restore the open circuit and the element should reset.

Table of Contents

Other manuals for GE 750

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE 750 and is the answer not in the manual?

GE 750 Specifications

General IconGeneral
BrandGE
Model750
CategoryRelays
LanguageEnglish

Related product manuals