GE Healthcare Senographe DS
Revision 1 Service Information and Procedures Class A 2385072-16-8EN
Job Card PM A205 - Mechanical checks and lubrication
Page no. 1779 Chapter 11
JC-PM-A-205.fm
Job Card PM A205 - Mechanical checks and lubrication Chapter 11
1SUPPLIES
• Lubricant
• Grease (for Lift and Rotation)
2TOOLS
Standard Tool Box
3 REQUIRED EFFORT
Personnel: 1 Field Engineer
Time: 20 minutes
4 SAFETY PRECAUTIONS
WARNING
Before working on any Gantry mechanism, shut down the equipment and switch OFF the
Senographe hospital supply circuit breaker. Lock it in the OFF position or mark it clearly
with a warning sign to prevent others from applying power.
• NEVER switch off at the UPS except in emergency (risk of data loss).
5 PREREQUISITES
• The Gantry Column and Compression Arm covers must be removed. Refer to Job Card PHY A044 -
Remove/Reinstall Gantry Covers on page 523.
• Release the four hex head screws securing the lower X plate (10 mm open-ended wrench).