1CONTEXT
This scenario provides a check list for use in planning and carrying out a pre-purchase site visit.
2STEERING GUIDE
# Requirement Reference Who? Done?
Altitude
1 Check that product specifications are
compatible with the altitude of the site
Chapter 4 Pre-Installation
System Requirements,
section 1 Environmental
Requirements
Hospital engi-
neer
Operating conditions
2 Check that operating the temperature
and humidity requirements can be met
Chapter 4 Pre-Installation
System Requirements,
section 1 Environmental
Requirements
Heating engineer
Rom layout
3 Check that an adequate room is avail-
able, with suitable floor and access
Chapter 4 Pre-Installation
System Requirements
Site planner
Electrical supply
4 Check availability of suitable supply Chapter 4 Pre-Installation
System Requirements,
section 5 Electrical
Requirements
Hospital engi-
neer
Networking
5 Check possibility of connection to hos-
pital network
Chapter 4 Pre-Installation
System Requirements,
section 12 Networking
Connections
Hospital engi-
neer, GEMSE
HMS representa-
tive
Insite connection
6 Check availability and type of broad-
band connection
Chapter 4 Pre-Installation
System Requirements,
section 11 Insite Connec-
tion
Hospital engi-
neer