1CONTEXT
This scenario provides a check list for use in planning and carrying out pre-installation work.
2STEERING GUIDE
# Requirement Reference Who? Done?
Pre-purchase site visit
1 Visit the proposed site to check for any potential
problems associated with installation.
Scenario PRE A002 - Pre-
purchase Site Visit
GEMS sales rep-
resentative
Purchase Senographe system
2 Order Senographe system with all appropriate
options from the Price Book.
For customers in all countries except China,
order the optional line supply cable. For custom-
ers in China, order an equivalent CCC-certified
line supply cable from the Price Book. For more
information see Line Supply Cable on page 337.
GEMS sales rep-
resentative
3 If the floor thickness is less than 120 mm and/or
the installation is in a seismic area, order different
anchoring bolts to those that are supplied with
the system.
Anchoring Inserts on page
354
Installation planning visit
4 Visit site to assess installation requirements and
specify the preparatory work required before
delivery and installation.
Scenario PRE A003 -
Installation Planning Visit
GEMS site plan-
ner
Preparatory work
5 Hospital or third-party contractors carry out pre-
paratory work.
Hospital
Pre-delivery check
6 Visit site to confirm that the preparatory work is
satisfactory and the site is ready for delivery and
installation.
Scenario PRE A004 - Pre-
Delivery Check
GEMS site plan-
ner
Delivery and storage
7 System delivery to designated storage. Chapter 4 Pre-Installation
System Requirements,
section 9 Planning for Stor-
age
Delivery person-
nel and hospital
Installation
8 System installation. GEMS installa-
tion engineers