Huawei will not be liable for any consequence caused by the violation of this
document.
The requirements are as follows:
● Customers' installation personnel must be trained by Huawei and understand
how to install and operate a modular data center.
● The number of installation personnel varies based on the project progress and
installation environment. Typically, two to three persons are required.
4.1.3 Installation Environment Check
Ensure that the installation environment meets the requirements before
installation.
Table 4-3 Installation environment checklist
Check Item Specications Check Result
Bearing capacity ● Standard live load of the computer
room: 8–12 kN/m
2
● Suspended load of the main
equipment room: 1.2 kN/m
2
● Standard live load of the battery
room: 16 kN/m
2
□ Passed □ Failed
Levelness Allowed deviation: 3/2000 mm □ Passed □ Failed
Equipment room
height
≥ 2.6m □ Passed □ Failed
Equipment room
area
8-30 m
2
□ Passed □ Failed
Door size Height > 2.2 m; width > 0.9 m □ Passed □ Failed
Elevator Elevator bearing capacity > 1.5 t
Elevator internal size: height > 2.4 m,
depth > 1.4 m
Elevator door size: height > 2.2 m; width
> 0.9 m
□ Passed □ Failed
Power supply 380 V AC/400 V AC/415 V AC, 3 Ph, 50
Hz/60 Hz
□ Passed □ Failed
Lighting ● Equipment room: 500 lx
● Monitoring center: 500 lx
● Test area: 500 lx
□ Passed □ Failed