Roche Diagnostics
E-64 Operatorโs Manual ยท Version 3.1
14 ISE maintenance Cedex Bio System
ISE maintenance actions
Deactivating the ISE unit
If you intend not to use the ISE unit for more than one week, you should deactivate it.
This saves ISE fluids and reduces wear and tear of the tubing, and lowers the
likelihood of malfunctions and errors occurring.
This situation may occur, for example, if you need close the laboratory temporarily,
or if you want to relocate the Cedex Bio instrument with the ISE unit.
Tools and materials required m Glass beaker
m Deionized water
m Tissues
a To prepare the ISE data
1
Delete all ISE sample, calibration, and control results.
e
See Deleting sample results on page B-94, Deleting calibration results on page B-95,
Deleting QC results on page B-96.
2
Disable all ISE applications.
e
See Activating and deactivating applications on page B-139.
3
Delete the ISE lot data.
e
See Lot handling on page B-98.
a To deactivate the ISE unit
1
Open the ISE cover.
2
Remove the tubing adapters from the ISE solution bottles.
3
Place the adapters in a beaker filled with deionized water.
4
Remove bottles and screw on their lids.
5
Place the beaker in the position where your removed the ISE solution bottles
from.
6
Choose Utilities > Maintenance > Prime ISE Reference and Calib.
7
Press .
The maintenance definition screen is displayed.
8
Press to start the action.
The ISE unit tubing is primed with water.
A message will inform you when the maintenance action is complete.
9
Repeat steps 6 through 8.
10
Remove the adapters from the beaker and place them on a lint-free tissue.
11
Repeat steps 6 through 8.
The water is drained from the ISE unit tubing.
Make sure that you have read and understood section Safety information on page E-42.
The following warning message in particular is relevant:
o Injury through working solutions on page E-42.
o Infection by biohazardous materials on page E-42