2.
Highlight
the Project File to be imported, and tap ENTER
button.
The Project File is set.
REMARK
Even if the currently selected Project File is highlighted, it
cannot be selected by ENTER button.
3.
After setting is completed, the name of currently selected
Project
File is displayed in “Current Project:” on “Project
File Settings” screen.
4.
Tap RETURN button and the screen returns to “Project
File Settings” screen.
CREATE NEW PROJECT FILE
Project File can be newly created on the intelligent Machine Control system or can be created on the basis of
the currently selected Project File or the Project File which is obtained via Site-Link.
REMARK
If a large capacity of data is saved in the control box, hard disk is used fully and the control box may not operate
normally. Delete unnecessary data frequently.
1.
Tap “Project Files” button.
2.
Tap “New” button and “New Project” screen is displayed.
METHOD FOR CREA
TING NEW PROJECT FILE
1.
Tap ENTER button without putting a tick to the following 2
items on “New Project” screen.
•
“Control points, localization, MM-GPS data”
• “Site-Link Connection details”
CONTROL BOX SETTING
7-6