16.3.1 Commissioning
In the following chapters, the steps required for controlling the inverter with a IO-Controller
via PR
OFINET are described.
Precondions
•
As an IO-De
vice, the inverter is connected to an IO-Controller and further PROFINET nodes
if required.
See "Typical topologies" under: 4PROFINET ^ 330
•
The enre wiring has been checked for completeness, short circuit and earth fault.
•
All PR
OFINET devices are supplied with voltage and are switched on.
•
The funconal test described in the mounng and switch-on instrucons has been com-
pleted successfully (without any errors or faults).
•
The inverter is commissioned with the »EASY Starter«.
•
Download »EASY Starter«
•
The IO-Controller is commissioned with a dierent engineering tool, e. g. Sie-
mens »TIA Portal«.
For this purpose, install the required GSDML device descripon le in the engineering tool
for the IO-Controller for conguring the inverter.
We always recommend the use of the current device descripon.
•
Do
wnload of GSDML les
•
Please ob
serve the necessary system requirements and the notes regarding the inver-
ter.
4Device descripon le ^ 333
16.3.1.1 Sengs in the »EASY Starter«
1.Set the IP address and the staon name ("PROFINET device name").
See: 4
Staon name and IP conguraon ^ 334
2.
Save the parameters in the inverter with mains failure protecon. 40x2022:003
See: 4Saving the parameter sengs ^ 36
3.
R
estart the PROFINET communicaon. 40x2380
See: 4Restarng or stopping the communicaon ^
332
Conguring the network
PR
OFINET
Commissioning