6.1 Bedplate
6.1.1 Bedplate - do a check of the foundation bolts
Periodicity
Description
One Time - after first working hours 1 500
Working hours 12 000
Duration for performing preliminary requirements 1.0 man-hours
Duration for performing the procedure 3.0 man-hours
Duration for performing the requirements after job completion 0.5 man-hours
Personnel
Description Specialization QTY
Engine crew Intermediate 2
Support equipment
Description Part No. CSN QTY
Feeler gauge 94122 1
Pre-tensioner 94145 1
HP oil pump 94931 1
Hydraulic distributors 94934A 2
HP hose 94935 1
Supplies
Description QTY
None
Spare Parts
Description Part No. CSN QTY
None
SAFETY PRECAUTIONS
WARNING
Injury Hazard: Hydraulic tools can cause injury to personnel. Always put on gloves, a
face shield and safety goggles when you do work with hydraulic tools.
PRELIMINARY OPERATIONS
• The engine must be stopped and made safe for maintenance, refer to section 4.1 Do
maintenance work - general procedure
X72DF
AA00-1115-00AAA-360A-A
Maintenance Manual Bedplate - do a check of the foundation bolts
Winterthur Gas & Diesel Ltd.
- 102 - Issue 002 2020-10