7.2.3 Lubricating quill - install
Periodicity
Description
Unscheduled at each piston removal
Duration for performing preliminary requirements 0.0 man-hours
Duration for performing the procedure 1.0 man-hours
Duration for performing the requirements after job completion 0.0 man-hours
Personnel
Description Specialization QTY
Engine crew Basic AR
Support equipment
Description Part No. CSN QTY
None
Supplies
Description QTY
Oil A/R
Spare Parts
Description Part No. CSN QTY
Lubricating quill A/R
SAFETY PRECAUTIONS
• None
PRELIMINARY OPERATIONS
• None
X72DF
AA00-2138-00AAA-720A-A
Maintenance Manual Lubricating quill - install
Winterthur Gas & Diesel Ltd.
- 198 - Issue 002 2020-10