8.3.2 Axial vibration damper - assemble
Periodicity
Description
Working hours 42 000
Duration for performing preliminary requirements 0.0 man-hours
Duration for performing the procedure 1.0 man-hours
Duration for performing the requirements after job completion 0.0 man-hours
Support equipment
Description Part No. CSN QTY
Spur-geared chain block 94016-2.5-5.5 1
Eye bolt 94045-M30 2
Chain 94325 1
Shackle 94019P 2
Sling 94038-011 2
Link 94321P 1
Supplies
Description QTY
Oil A/R
Molykote paste G A/R
Spare Parts
Description Part No. CSN QTY
Two-part gasket 2
Two-part gasket 1
SAFETY PRECAUTIONS
• None
PRELIMINARY OPERATIONS
• The engine must be stopped and made safe for maintenance, refer to section 4.1 Do
maintenance work - general procedure
X72DF
AA00-3140-00AAA-710A-A
Maintenance Manual Axial vibration damper - assemble