12.2.10 Integrated electric balancer - install the bearing (outer side)
Periodicity
Description
Unscheduled
Duration for performing preliminary requirements 0.0 man-hours
Duration for performing the procedure 0.5 man-hours
Duration for performing the requirements after job completion 0.0 man-hours
Personnel
Description Specialization QTY
Engine crew Intermediate AR
Support equipment
Description Part No. CSN QTY
Lifting tool 94704 1
Supplies
Description QTY
Molykote D AR
Loctite No. 640 AR
Spare Parts
Description Part No. CSN QTY
Bearing 1
SAFETY PRECAUTIONS
CAUTION
Injury Hazard: Use the correct equipment to lift and move the bearing. This will prevent
injury to personnel and damage to equipment.
NOTE: Do not install the taper pins during this procedure.
PRELIMINARY OPERATIONS
• None
X72DF
AA00-7758-00AAA-720B-A
Maintenance Manual Integrated electric balancer - install the bearing (outer side)