10.5.3 Fuel rail - install the pressure control valve
Periodicity
Description
Unscheduled
Duration for performing preliminary requirements 0.0 man-hours
Duration for performing the procedure 0.5 man-hours
Duration for performing the requirements after job completion 0.0 man-hours
Personnel
Description Specialization QTY
Engine crew Basic AR
Support equipment
Description Part No. CSN QTY
None
Supplies
Description QTY
Never-Seez NSBT-8 A/R
Spare Parts
Description Part No. CSN QTY
O-ring 1
O-ring 1
SAFETY PRECAUTIONS
• None
PRELIMINARY OPERATIONS
• None
X72DF
AA00-5562-00AAA-720A-A
Maintenance Manual Fuel rail - install the pressure control valve
Winterthur Gas & Diesel Ltd.
- 590 - Issue 002 2020-10