11.2 Auxiliary blower
11.2.1 Auxiliary blower - remove
Periodicity
Description
Working hours 30 000
Duration for performing preliminary requirements 0.0 man-hours
Duration for performing the procedure 1.5 man-hours
Duration for performing the requirements after job completion 0.0 man-hours
Personnel
Description Specialization QTY
Engine crew Basic AR
Support equipment
Description Part No. CSN QTY
Spur-geared chain block 94017-2.5-6-5 2
Spur-geared chain block 94017-2.5-5-4 3
Shackle 94019L 2
Shackle 94019K 1
Shackle 94019H 3
Slings 94039-013 2
Trolley 94015F 1
Lifting tool 94651 1
Supplies
Description QTY
None
Spare Parts
Description Part No. CSN QTY
None
SAFETY PRECAUTIONS
WARNING
Use only applicable equipment to lift and move the electric motor.
PRELIMINARY OPERATIONS
The engine must be stopped and made safe for maintenance, refer to section 4.1 Do
maintenance work - general procedure
X72DF
AA00-6545-00AAA-520A-A
Maintenance Manual Auxiliary blower - remove
Winterthur Gas & Diesel Ltd.
- 634 - Issue 002 2020-10

Table of Contents

Questions and Answers:

WinGD X62DF Specifications

General IconGeneral
BrandWinGD
ModelX62DF
CategoryEngine
LanguageEnglish

Related product manuals