7.3 Gas admission valve
7.3.1 Gas admission valve - do a check of the oil leakage flow
Periodicity
Description
Working hours 6000
Duration for performing preliminary requirements 0.0 man-hours
Duration for performing the procedure 0.5 man-hours
Duration for performing the requirements after job completion 0.0 man-hours
Personnel
Description Specialization QTY
Engine crew Basic AR
Support equipment
Description Part No. CSN QTY
Measuring tool N/A 1
Pressure reducing valve 94214B 1
Supplies
Description QTY
Lubricating oil (SAE 30) A/R
Spare Parts
Description Part No. CSN QTY
None
SAFETY PRECAUTIONS
• None
PRELIMINARY OPERATIONS
• The engine must be stopped and made safe for maintenance, refer to section 4.1 Do
maintenance work - general procedure
X72DF
AA00-2140-00AAA-363A-A
Maintenance Manual Gas admission valve - do a check of the oil leakage flow
Winterthur Gas & Diesel Ltd.
- 202 - Issue 002 2020-10